| Jefferson Elementary School |
|
{Jefferson} |
Location: 4628 Mistletoe
Architect: Bundy, Young, Sims & Potter
Project Architect/Engineer: TBD
Anticipated Finish Date: 8/2010
Status: Site work foundation pad prep | |
|
Project |
Method |
Contractor |
% Complete |
Start Date |
Original Cost |
Final Cost |
| Driveway modifications and additions |
CSP |
TBD |
100% |
6/1/2008 |
$239,800 |
$141,228 |
| Exterior door replacements |
CSP |
TBD |
100% |
9/1/2009 |
$59,950 |
$64,271 |
| Media center |
GC |
TBD |
0% |
6/1/2010 |
$81,750 |
|
| Replace 1 classroom |
GC |
TBD |
100% |
6/1/2010 |
$163,500 |
$246,750 |
| Add 2 classrooms |
GC |
TBD |
100% |
11/1/2009 |
$327,000 |
$751,738 |
| Window/panel replacements |
GC |
TBD |
0% |
6/1/2010 |
$365,150 |
|
| Bathroom renovations |
WFISD |
TBD |
50% |
1/1/2010 |
$81,750 |
|
| Replace 38 heat., vent, & AC systems |
CSP |
TBD |
100% |
6/1/2010 |
$305,200 |
$226,974 |
| Kitchen equipment and remodeling |
WFISD |
TBD |
100% |
6/1/2010 |
$27,250 |
$40,850 |
| Teaching gym |
GC |
TBD |
100% |
11/1/2009 |
$599,500 |
$1,278,578 |
| Replace electrical switchgear |
CSP |
TBD |
100% |
6/1/2009 |
$119,900 |
$118,621 |
| Furnishings |
CSP |
TBD |
100% |
6/1/2009 |
$0 |
$5,602 |
| Site Drainage Improvement |
WFISD |
TBD |
100% |
6/1/2009 |
$0 |
$41,064 |
| Location Totals |
|
|
|
|
$2,370,750 |
| |
|